A project is broken down into 8 tasks–A to H–with given duration times and predecessors.
Task | Duration | Predecessor |
A | 3 | |
B | 4 | |
C | 4 | A, B |
D | 5 | A |
E | 2 | A, B |
F | 8 | C, D |
G | 4 | D, E |
H | 3 | F, G |
- Draw the task relationships diagram, and identify earliest start/finish times, as well as latest start/finish times, slack, and critical path. (60 points)
- Draw the Gantt chart and identify the critical path and slacks with different colors. (40 points)